Across Europe, thousands of civil defence shelters were built during the Cold War. Many of them still exist beneath residential buildings, schools, hospitals, industrial facilities, municipal and government buildings, residential properties and critical infrastructure.


The structures are still there. The more important question is whether they are still operational.

Over the last several years, Atmas Group teams have visited and inspected hundreds of existing civil defence shelters and protected facilities across different countries as part of renovation, modernization, equipment supply and project assessment work.

These have included shelters in schools, hospitals and healthcare facilities, industrial sites, municipalities, government buildings, residential properties, public facilities and critical infrastructure, as well as larger dedicated civil defence shelters and protected facilities.

The condition of these shelters varies considerably.

Some have been maintained well and remain in relatively good structural and technical condition. Others have strong reinforced-concrete structures but technical equipment that is several decades old.

We have also inspected shelters where much of the original equipment was missing or in very poor condition. Filtration systems had been removed, ventilation components were damaged, protective doors had deteriorated and openings had been made through shelter walls for pipes, cables and other building services.

Water and moisture are also common problems. Some shelters we have visited had been flooded or exposed to water ingress for extended periods.

Others had simply received very little attention for decades or had been used mainly for storage.

Another common issue is missing documentation. Original drawings, structural plans, ventilation diagrams and equipment documentation may be incomplete or no longer available.

In other cases, drawings exist but no longer represent the actual condition of the shelter after decades of modifications.

Despite these problems, many older shelters still contain something extremely valuable: the original protective structure.

Where that structure remains suitable, renovation can often be a practical alternative to constructing a completely new shelter.


Renovation Versus a New Shelter Project

There can also be an important practical advantage to retaining the original shelter configuration.

In some countries and under certain local regulations, replacement of existing shelter equipment with modern equipment of the same or equivalent function and configuration may be treated as a replacement or renovation project rather than a completely new shelter project.

Where permitted by the applicable regulations and accepted by the relevant authorities, this can significantly reduce the amount of redesign, construction and approval work required.

For example, an old filtration system may sometimes be replaced with a modern equivalent while retaining suitable existing air intakes, wall penetrations, duct routes and the general ventilation arrangement.

The same principle can sometimes apply to blast valves, overpressure valves, protective doors, hatches and other shelter equipment.

This can considerably shorten the renovation process compared with redesigning the complete shelter from the beginning.

However, this approach cannot be assumed for every project.

Requirements vary between countries and may depend on shelter classification, local regulations, the extent of the modifications and the condition of the existing installation.

The first task is therefore to understand what already exists and determine what can reasonably and legally remain in use.


1. Inspection, Assessment and Documentation

A proper technical assessment should be the starting point for any shelter renovation.

This is particularly important because the information available about an older shelter may be limited.

A shelter constructed 40 or 50 years ago may have changed considerably since its original construction.

Ventilation systems may have been modified. Electrical installations may have been replaced. Pipes and cables may have been routed through protective walls. Equipment may have been removed. Rooms may have been modified.

In many cases, these changes were never properly documented.

Sometimes the original shelter drawings simply cannot be found.

For this reason, renovation often starts with documenting the shelter as it actually exists today.

The assessment may include shelter dimensions, structural elements, entrances and emergency exits, protective doors and hatches, ventilation routes, air intakes and exhausts, wall penetrations, blast and overpressure valves, technical rooms, electrical installations, water and sewage connections and existing shelter equipment.

Where drawings are available, they should be compared with the actual installation rather than automatically assumed to be correct.

This initial assessment helps answer the main questions of the renovation:

What can remain? What can be repaired? What needs to be replaced? And what is missing completely?


Assessment of an existing civil defence shelter before modernization.
Assessment of an existing civil defence shelter before modernization.

2. Structural Condition and Reinforcement

The reinforced-concrete structure is usually the most valuable part of an existing shelter.

Many Cold War shelters were constructed with substantial reinforced-concrete walls and ceiling slabs. In many cases these structures can remain serviceable for decades.

But their condition needs to be verified.

The inspection should consider visible cracking, concrete deterioration, reinforcement corrosion, construction joints, existing openings, previous modifications and signs of water damage.

It is also important to consider whether changes to the surrounding building have affected the original shelter structure.

If problems are identified, modernization may include concrete repairs, local structural reinforcement, strengthening around openings or additional protective elements.

The objective should not automatically be to rebuild the shelter.

If the original structure remains suitable, it makes sense to preserve as much of it as possible and concentrate renovation work on the areas where it is actually required.


Assessment and renovation of an existing reinforced-concrete shelter structure.
Assessment and renovation of an existing reinforced-concrete shelter structure.


3. Water Damage and Flooding

Water is one of the problems we repeatedly encounter in older underground shelters.

Some facilities have suffered occasional flooding. Others have experienced water ingress or high moisture levels for years.

The concrete structure may survive these conditions relatively well, but shelter equipment often does not.

Water can damage electrical installations, ventilation equipment, valves, door mechanisms and other steel components.

Corrosion can develop, stored equipment can be destroyed and technical rooms can become unusable.

Installing new shelter equipment without solving the underlying water problem makes little sense.

Where water ingress is present, the source should therefore be identified as part of the renovation.

Depending on the facility, work may include drainage improvements, waterproofing, pumping arrangements, sealing, drying and repair of affected structures.

Only after the problem is under control should new protective equipment be installed.


Water ingress and long-term moisture are common problems in older underground shelters.
Water ingress and long-term moisture are common problems in older underground shelters.


4. CBRN Filtration and Ventilation Systems

Ventilation and filtration equipment is one of the most common areas requiring complete modernization.

A reinforced-concrete shelter may remain serviceable for many decades. Mechanical equipment, filters, seals, bearings and electrical components have a very different lifecycle.

We have inspected shelters where the original filtration equipment was still present but had clearly not operated for many years.

In others, parts of the ventilation system were missing.

And in some shelters, practically the entire original filtration installation had been removed.

The existence of an air intake, ventilation room or old filtration unit therefore does not mean that the shelter still has functioning protected ventilation.

The system needs to be assessed as a whole.

This includes the outside air intake, blast protection, shut-off devices, ductwork, filtration equipment, blower, electrical supply, manual backup where applicable, shelter overpressure and protected exhaust.


Replacement of Existing Filtration Equipment

Where the original configuration remains suitable, modern CBRN filtration equipment can often be integrated into the existing shelter infrastructure.

Existing air intakes, wall penetrations and duct routes may be retained where their condition, dimensions and arrangement are suitable.

This can significantly reduce the amount of construction work required.

Several old filtration units can also sometimes be replaced by a more efficient modern configuration.

Wall-mounted filtration systems can be particularly useful in existing shelters because they allow valuable floor space to remain available for people, equipment and storage.

However, the objective should never be simply to remove an old filter and install a new one.

The objective is to restore a complete functioning protected ventilation system.



Replacement of ageing shelter ventilation equipment with a modern CBRN filtration system.
Replacement of ageing shelter ventilation equipment with a modern CBRN filtration system.


5. Protective Doors and Hatches

Protective doors and hatches are another major part of shelter renovation.

Interestingly, some old blast doors are still in relatively good condition. They were often heavily constructed, and the main door leaf and frame may remain usable after several decades.

However, this cannot be determined from appearance alone.

Seals may have deteriorated. Hinges and bearings may require servicing. Locking mechanisms may not operate correctly. Frames and anchoring points may be corroded or damaged.

The first decision is therefore whether the existing closure can be repaired or whether replacement is more appropriate.


Repair

Where the original door remains technically suitable, work may include corrosion treatment, replacement of seals, adjustment, lubrication and repair of hinges, handles and locking mechanisms.

Keeping the original door can be the simplest and most economical solution where its basic condition and protection level remain acceptable.


Retrofit

In other cases, the existing opening and surrounding structure remain suitable but the original door or hatch does not.

A retrofit solution can allow modern protective equipment to be installed while retaining much of the existing reinforced-concrete opening.

This is particularly valuable in underground structures, where unnecessary cutting and reconstruction of heavily reinforced concrete can add significant cost and time.


Replacement

Where the existing door or hatch is damaged, incomplete, heavily corroded or unsuitable for the required protection level, complete replacement may be necessary.

The new closure should always be considered together with its frame, anchoring and surrounding structure.

A modern protective door is only as effective as the structure into which it is installed.


Existing protective doors can be repaired, retrofitted or replaced depending on their condition.
Existing protective doors can be repaired, retrofitted or replaced depending on their condition.


6. Blast and Overpressure Valves

Blast and overpressure valves are relatively small components compared with the shelter structure, but they have an important role in protected ventilation.

Many old shelters still contain their original valves.

After several decades, corrosion, mechanical damage, contamination or lack of maintenance can affect their operation.

They should therefore be inspected together with the rest of the ventilation system.

Where existing wall sleeves and openings remain suitable, they can often be reused for modern blast and overpressure valves.

This is another area where retaining existing infrastructure can simplify renovation and reduce the need for new openings through reinforced-concrete walls.

However, the dimensions, condition and installation of the existing opening need to be verified before new equipment is selected.


Modern blast and overpressure valves can often be integrated into existing shelter ventilation openings.
Modern blast and overpressure valves can often be integrated into existing shelter ventilation openings.


7. Penetrations and Airtightness

One of the less visible but important problems in older shelters is the gradual loss of integrity of the protective envelope.

Buildings change over time.

New electrical cables are installed. Water and heating pipes are added. Telecommunications lines are routed through walls. Old equipment is removed and openings are left behind.

For ordinary building spaces, these modifications may not create a major problem.

For a civil defence shelter, they can.

Some penetrations may have been made through walls or ceilings without considering the protective function of the structure.

All existing penetrations should therefore be identified during renovation.

Unnecessary openings can be closed, while required penetrations should be properly protected and sealed.

Airtightness is particularly important for shelters operating under positive pressure during CBRN conditions.

Door seals, duct connections, wall penetrations and unused openings can all contribute to leakage.

A modern filtration system can supply filtered air, but excessive leakage may prevent the shelter from maintaining the required overpressure.

Restoring airtightness is therefore often an important part of renovation.

After the work is completed, pressure and leakage testing can be used to verify the result.


8. Emergency Exits

Emergency exits also require physical inspection.

This is particularly important when original drawings are missing or several decades old.

The building and surrounding area may have changed considerably since the shelter was constructed.

An escape route may have been obstructed, covered by later construction or modified during building renovation.

Protective hatches may be corroded, damaged or difficult to operate.

The complete route should therefore be checked, including the internal access, protective closure and the area outside the shelter.

An emergency exit shown on an old drawing has little value if it can no longer be used.


Restored emergency exit hatch and stairs in an old civil defence shelter
Restored emergency exit hatch and stairs in an old civil defence shelter

9. Water, Sanitation and Electrical Systems

Once the main protective systems have been addressed, the basic services required for shelter operation also need to be considered.

Water supply, sanitation and wastewater arrangements should reflect the intended shelter capacity and expected operating period.

Normal municipal services cannot always be assumed to remain available during a major emergency.

Depending on the shelter, modernization may therefore include emergency water storage, independent sanitation arrangements, wastewater tanks, pumps or other backup solutions.

Electrical power requires similar consideration.

Modern ventilation, lighting, pumps, monitoring and communication equipment may all depend on electricity.

Backup power may therefore include generators, UPS systems, batteries or other independent sources depending on the facility.

For critical shelter equipment, manual backup operation can also be valuable.

The requirements for a residential shelter will naturally be different from those for a hospital, industrial facility or large municipal shelter.

The technical solution should reflect the actual intended use of the facility.


10. Monitoring and Shelter Equipment

Modernization is also an opportunity to improve monitoring of the shelter environment.

Depending on the facility, this can include shelter pressure, CO₂ concentration, temperature, humidity and other relevant parameters.

This provides the operator with much better information about what is happening inside the protected space and whether the ventilation system is operating correctly.

For larger shelters or facilities intended for longer periods of operation, additional air-management equipment such as CO₂ removal may also be considered.

Other shelter equipment should also be reviewed.

In many older shelters we have inspected, some or most of the original equipment was no longer present.

Emergency lighting, communications, firefighting equipment, medical supplies, tools, protective equipment and other practical items may have disappeared during decades of normal building use.

The required equipment should therefore be checked based on the intended use of the shelter rather than assumed to be present because it appears in an old equipment list.


11. Testing and Commissioning

Renovation should not finish when the installation work is complete.

The shelter and its systems should be tested.

The extent of testing depends on the facility and applicable requirements, but it may include protective doors and hatches, ventilation airflow, filtration system operation, shelter overpressure, leakage, blast and overpressure valves, backup operation, electrical systems, emergency lighting, water systems and emergency exits.

This is especially important when modern equipment is being connected to infrastructure constructed several decades earlier.

Each component may work individually, but the shelter needs to operate as a complete system.

Testing and commissioning provide the opportunity to identify problems before the facility is actually required.

Documentation should also be updated after the renovation.

This is important because one of the difficulties we face today is precisely the lack of documentation from previous decades.

A shelter renovated today should not create the same problem for somebody inspecting it 30 years from now.


Modernization of Existing Civil Defence Infrastructure

Having visited and inspected hundreds of existing shelters in recent years, Atmas Group teams have seen very different conditions across schools, hospitals, industrial facilities, municipalities, residential buildings, public facilities and critical infrastructure.

We have found well-preserved structures with obsolete equipment. We have found shelters where filtration systems, valves or other equipment were missing.

We have seen protective doors that could be repaired and others that required replacement. We have encountered flooded technical rooms, damaged ventilation systems, undocumented penetrations and shelters where the original drawings could no longer be found.

But we have also seen that many of these facilities can be restored.


The approach should be practical.

Inspect what exists.

Document its actual condition.

Determine what can remain.

Repair what makes sense to repair.

Replace what can no longer provide the required function.

And test the shelter after the work is completed.


Atmas Group provides solutions for both new civil defence shelters and modernization of existing protected facilities.

Depending on the project, this can include CBRN filtration and ventilation systems, blast and overpressure valves, protective doors and hatches, retrofit solutions, structural protection, protected penetrations, water and wastewater solutions, backup systems, monitoring and other shelter equipment.

Our equipment and solutions have already been integrated into existing shelter renovation projects in different markets, providing practical experience of the challenges involved in bringing older civil defence infrastructure back into operational condition.


Before and After – Shelter Renovation

The initial condition of an old shelter can sometimes look discouraging.

Equipment may be corroded or missing. Technical rooms may have been flooded. Protective doors may no longer close correctly. Ventilation systems may not operate.

Drawings may be unavailable, and decades of undocumented building modifications may first need to be understood.

This does not necessarily mean that the shelter has reached the end of its useful life.

Where the basic protective structure remains suitable, renovation can restore its main protective functions while retaining a significant part of the original construction.


Examples of recent renovations by Atmas Group


Replacment of old CBRN filtration systems with modern systems in Poland
Replacment of old CBRN filtration systems with modern systems in Poland
Complete shelter renovation with Atmas equipment in a Municipal shelter
Complete shelter renovation with Atmas equipment in a Municipal shelter

Hospital shelter renovation with new CBRN filtration system
Hospital shelter renovation with new CBRN filtration system

Replacment of CBRN filters and accessories in a large civil defence shelter
Replacment of CBRN filters and accessories in a large civil defence shelter

Renovation of existing blast doors in a shelter
Renovation of existing blast doors in a shelter

Conclusion

Europe has a significant amount of existing civil defence infrastructure.

Some shelters remain operational. Some require relatively limited modernization. Others have been neglected for decades and require substantial work before they can again be considered ready for use.

Original drawings may be missing. Equipment may have disappeared. Ventilation systems may no longer operate. Protective doors may require repair or replacement.

Shelters may have been flooded. New penetrations may have been made through protective walls, and emergency exits may no longer correspond to the original plans.

At the same time, the reinforced-concrete structure may remain in good condition and represent a valuable civil defence asset.

This is why the age of a shelter alone tells us relatively little about its actual value.

Each existing shelter should be assessed individually to determine what can be retained, what needs to be repaired and what needs to be replaced.

In some countries, retaining the original configuration and replacing obsolete equipment with modern equivalents can also simplify the renovation and approval process compared with designing a completely new shelter solution.

Europe will need new civil defence infrastructure, but existing shelters should not be overlooked.

In many cases, the most difficult and expensive part has already been built.

The task is to assess its real condition, modernize the systems that need modernization and bring the shelter back into operational use.